Ultrasonic bottle washer operating procedures:
1. Prepare (1) Check the equipment electrical switch, the meter indicates, the equipment drive is normal.
(2) Check if the dial bottle clutch is in the normal position, if it is in the neutral position, please adjust it.
(3) Close the machine power switch, turn on the speed switch, the inverter operation panel fluorescent screen displays the setting frequency. At this time, press the RUN button, the inverter works, and the motor speed gradually reaches the set value. Stop pressing the STOP button.
(4) Run the machine for 2 minutes to check whether the equipment and mechanical transmission structure are normal, whether the operation sound is normal, and the production can be performed normally.
2. Start the water inlet valve first, fill the liquid storage tank with water, open the salt-free valve, open the water injection valve, spray the water normally, open the water pump switch, fill the ultrasonic cleaning tank with water, adjust the water inlet, and make the tank Keep a certain water level (do not open the ultrasonic wave below the water level) and open the air valve. When the water level in the tank reaches the specified water level, the ultrasonic switch is turned on, and the ultrasonic cleaning machine enters the bottle washing state.
(1) The operator puts the vial into the bottle tray and turns on the speed switch to make the rotation speed 10~26Hz (100~400/min 7ML). Press RUN to start production.
(2) When there is a bottle condition, first press the STOP button to stop, check the bottle bottle part, clean the broken bottle in time, adjust the bottle wheel, and then drive production.
(3) Put the vial into the bottle wheel and the track in the bottle turntable. It is strictly forbidden to pour the bottle.
3. Note (1) It is strictly forbidden to open the ultrasonic wave without water level.
(2) After the end of production, the ultrasonic wave must be turned off first, then the water should be discharged.
(3) If the ultrasonic wave does not work, please consult the professional maintenance personnel.
(4) If you want to adjust the production volume, please set the required working frequency according to the inverter manual.
(5) It is strictly forbidden to pour the bottle into the track.
1. Prepare (1) Check the equipment electrical switch, the meter indicates, the equipment drive is normal.
(2) Check if the dial bottle clutch is in the normal position, if it is in the neutral position, please adjust it.
(3) Close the machine power switch, turn on the speed switch, the inverter operation panel fluorescent screen displays the setting frequency. At this time, press the RUN button, the inverter works, and the motor speed gradually reaches the set value. Stop pressing the STOP button.
(4) Run the machine for 2 minutes to check whether the equipment and mechanical transmission structure are normal, whether the operation sound is normal, and the production can be performed normally.
2. Start the water inlet valve first, fill the liquid storage tank with water, open the salt-free valve, open the water injection valve, spray the water normally, open the water pump switch, fill the ultrasonic cleaning tank with water, adjust the water inlet, and make the tank Keep a certain water level (do not open the ultrasonic wave below the water level) and open the air valve. When the water level in the tank reaches the specified water level, the ultrasonic switch is turned on, and the ultrasonic cleaning machine enters the bottle washing state.
(1) The operator puts the vial into the bottle tray and turns on the speed switch to make the rotation speed 10~26Hz (100~400/min 7ML). Press RUN to start production.
(2) When there is a bottle condition, first press the STOP button to stop, check the bottle bottle part, clean the broken bottle in time, adjust the bottle wheel, and then drive production.
(3) Put the vial into the bottle wheel and the track in the bottle turntable. It is strictly forbidden to pour the bottle.
3. Note (1) It is strictly forbidden to open the ultrasonic wave without water level.
(2) After the end of production, the ultrasonic wave must be turned off first, then the water should be discharged.
(3) If the ultrasonic wave does not work, please consult the professional maintenance personnel.
(4) If you want to adjust the production volume, please set the required working frequency according to the inverter manual.
(5) It is strictly forbidden to pour the bottle into the track.